KONČAR – Power Plant and Electric Traction Engineering Inc. has put into operation the Orikum and Himare substations in Albania

/KONČAR – Power Plant and Electric Traction Engineering Inc. has put into operation the Orikum and Himare substations in Albania
KONCAR - transformer substation Himare in Albania

As part of the construction of the 110 kV Circuit Line South Albania, two new substations, Orikum 110/35/20 kV and Himare 110/35/20 kv, have been put into operation.

KONČAR – Power Plant and Electric Traction Engineering Inc. (KET) prepared the complete project documentation, organized the construction and equipment assembly and testing, as well as the commissioning of the facilities.

Nearly 90 percent of the equipment for the two substations was manufactured by companies from the KONČAR Group.

In addition to KET, that included Switchgear Inc., Electronics and Informatics Inc., Instrument Transformers Inc., and Distribution & Special Transformers Inc.

With the construction of these two new facilities, the Albanian distribution system operator OSHEE has strengthened the power grid of this important tourist region.

2018-09-28T12:59:51+00:00 28. September 2018.|Categories: News|Tags: , , |